DEM Wetland Application #12-0117
- Applicant name
- Organization name Narragansett Electric Co.
- Location various North Smithfield
- Project information Interstate Reliability Project - Utility (Electric)
- Plan View
Location description
Along a Narragansett Electric Company powerline right-of-way on the "366" line from the Massachusetts border to the West Farnum Substation, and thence westward along the "341" line to the Connecticut border, through the Towns of North Smithfield and Burrillville, RI
Historical information
-
August 15, 2017Compliance w/ Approval-Project Completed
-
August 15, 2017Application Review by Supervisor
-
July 27, 2017Compliance Inspection
-
April 14, 2017Compliance Inspection
-
April 07, 2017Compliance Inspection
-
October 25, 2016Notice of Project Completion from Applct
-
December 28, 2015Compliance Inspection
-
November 12, 2015Modification Approved - Permit Issued
-
November 10, 2015Application Review by Supervisor
-
November 10, 2015Application Review by Biologist
-
October 16, 2015Application Review by Supervisor
-
October 07, 2015Request to Modify Wetland Permit
-
February 18, 2015Modification Approved - Permit Issued
-
February 18, 2015Application Review by Biologist
-
February 18, 2015Application Review by Supervisor
-
January 28, 2015Application Review by Supervisor
-
January 21, 2015Request to Modify Wetland Permit
-
April 14, 2014Modification Approved - Permit Issued
-
April 14, 2014Application Review by Supervisor
-
April 08, 2014Application Review by Biologist
-
February 27, 2014Application Review by Supervisor
-
February 24, 2014Date Start of Construction Notice Rec'd
-
February 24, 2014Request to Modify Wetland Permit
-
October 09, 2013Alteration Permit Issued
-
October 08, 2013Application Review by Supervisor
-
October 01, 2013Applicant Response to Tech. Deficiency
-
July 16, 2013Technical Deficiency Letter Sent
-
July 16, 2013Supervisor Review of Alteration Project
-
June 26, 2013Public Notice Comment Review
-
June 26, 2013Biologist Evaluation
-
June 03, 2013Water Quality Review
-
May 13, 2013Public Notice End Date
-
March 27, 2013Public Notice Issued
-
March 25, 2013Public Notice Plan Review
-
March 25, 2013Plans Received for Public Notice
-
February 20, 2013Adequate for Public Notice
-
February 20, 2013Application Review by Supervisor
-
February 14, 2013Application Review by Biologist
-
February 13, 2013Additional Info Received during Review
-
January 04, 2013Application Review by Engineer
-
December 19, 2012Applicant Response to Tech. Deficiency
-
September 20, 2012Technical Deficiency Letter Sent
-
September 20, 2012Application Review by Biologist
-
September 05, 2012Application Review by Engineer
-
July 30, 2012Supervisor for Assignment
-
July 27, 2012Additional Info Received during Review
-
July 12, 2012Request to Alter Wetland Application
Need to Review a File? Email a Request for Records Form to DEM.FileReview@dem.ri.gov.
For wetlands questions, please visit dem.ri.gov/wetlands or email DEM.FWW@dem.ri.gov.Last updated 04-08-2026 05:43 PM