DEM Wetland Application #19-0181
- Applicant name
- Organization name Albion Hydro, LLC
- Location School Street Cumberland
- Plat/Lot Plat 33 / Lot 431
- Project information Albion Dam Hydroelectric Project - Hydro Facility
- Plan View
- DEM Letter View
Location description
Approximately 450 feet northwest of Albion Road, and approximately 350 feet east of its intersection with School Street, Assessor's Plat 33, Lot 431, Cumberland, RI.
Historical information
-
December 10, 2024Permit Recorded in Land Evidence Record
-
November 21, 2024Notice of Project Completion from Applct
-
November 20, 2024Permit Renewal Granted
-
November 20, 2024Modification Approved - Permit Issued
-
November 20, 2024Application Review by Supervisor
-
October 31, 2024Application Review by Engineer
-
August 29, 2024Request to Renew Permit
-
August 29, 2024Response from Applicant
-
August 23, 2024Administrative Deficiency Letter Sent
-
July 24, 2024Request to Modify Wetland Permit
-
June 18, 2024Response to Nonconformance Received
-
May 02, 2024Nonconformance with Permit
-
May 02, 2024Permit Transfered
-
May 02, 2024Permit Renewal Granted
-
May 01, 2024Application Review by Supervisor
-
April 08, 2024Compliance Inspection
-
February 26, 2024Request to Renew Permit
-
February 26, 2024Wetland Transfer Request Received
-
December 31, 2022RIPDES Permit Fee Paid for Billing Year
-
June 01, 2022Application Review by Supervisor
-
May 23, 2022Request to Renew Permit
-
March 07, 2022Permit Recorded in Land Evidence Record
-
March 07, 2022Permit Recorded in Land Evidence Record
-
February 09, 2022Modification Approved - Permit Issued
-
February 09, 2022Application Review by Supervisor
-
February 09, 2022Application Review by Biologist
-
February 02, 2022Application Review by Supervisor
-
February 01, 2022Application Review by Biologist
-
January 27, 2022Applicant Response to Tech. Deficiency
-
November 04, 2021Technical Deficiency Letter Sent
-
November 04, 2021Application Review by Supervisor
-
October 28, 2021Request to Modify Wetland Permit
-
April 14, 2021Modification Approved - Permit Issued
-
April 14, 2021Application Review by Supervisor
-
March 04, 2021Request to Modify Wetland Permit
-
February 23, 2021Date Start of Construction Notice Rec'd
-
August 31, 2020Permit Recorded in Land Evidence Record
-
August 26, 2020Alteration Permit Issued
-
August 14, 2020Application Review by Supervisor
-
August 14, 2020Engineering Evaluation
-
July 29, 2020Public Notice Comment Review
-
July 29, 2020Biologist Evaluation
-
June 15, 2020Public Notice End Date
-
April 29, 2020Public Notice Issued
-
April 27, 2020Application Review by Supervisor
-
April 21, 2020Public Notice Plan Review
-
April 15, 2020Plans Received for Public Notice
-
April 13, 2020Adequate for Public Notice
-
April 13, 2020Application Review by Supervisor
-
April 09, 2020Application Review by Biologist
-
February 24, 2020Application Review by Engineer
-
February 24, 2020Water Quality Review
-
February 13, 2020Applicant Response to Tech. Deficiency
-
January 24, 2020Technical Deficiency Letter Sent
-
January 24, 2020Application Review by Biologist
-
January 09, 2020Application Review by Engineer
-
November 08, 2019Applicant Response to Tech. Deficiency
-
September 26, 2019Technical Deficiency Letter Sent
-
September 26, 2019Application Review by Supervisor
-
September 23, 2019Application Review by Biologist
-
August 28, 2019Application Review by Engineer
-
July 18, 2019Supervisor for Assignment
-
July 17, 2019Response to Administrative Deficiency
-
June 24, 2019Response from Applicant
-
June 19, 2019Response from Applicant
-
June 17, 2019Administrative Deficiency Letter Sent
-
June 17, 2019Supervisor for Assignment
-
June 07, 2019Request to Alter Wetland Application