DEM Wetland Application #21-0175
- Applicant name
- Organization name RI Resource Recovery Corporation
- Location Shun Johnston
- Plat/Lot Plat 31 / Lot 74
- Project information - Offices/Commerical (New)
- Plan View
- DEM Letter View
Location description
Approximately 250 feet south of Shun Pike, between Utility Pole Nos. 8-50 and 6-50, and approximately 270 feet southwest of its intersection with Simmons Lake Drive, Assessor's Plat 31, Lot 74, Johnston, RI.
Historical information
-
April 15, 2022Notice of Project Completion from Applct
-
December 31, 2021RIPDES Permit Fee Paid for Billing Year
-
October 04, 2021Date Start of Construction Notice Rec'd
-
September 30, 2021Permit Recorded in Land Evidence Record
-
September 24, 2021Insignificant Alteration Permit Issued
-
September 23, 2021Application Review by Supervisor
-
September 13, 2021Application Review by Biologist
-
September 10, 2021Application Review by Engineer
-
September 03, 2021Applicant Response to Tech. Deficiency
-
July 21, 2021Technical Deficiency Letter Sent
-
July 21, 2021Application Review by Biologist
-
July 19, 2021Application Review by Engineer
-
July 07, 2021Supervisor for Assignment
-
June 17, 2021Preliminary Determination Application
Need to Review a File? Email a Request for Records Form to DEM.FileReview@dem.ri.gov.
For wetlands questions, please visit dem.ri.gov/wetlands or email DEM.FWW@dem.ri.gov.Last updated 04-08-2026 05:43 PM