DEM Wetland Application #22-0471
- Applicant name
- Organization name RIDOT
- Location Route 146 North Smithfield
- Project information ROUTE 146 RECONSTRUCTION PROJECT - Road Reconstruction
Location description
Route 146 from the I-295 interchange to the Massachusetts state line. Assessor's Plat is a State Highway Layout. North Smithfield, RI.
Historical information
-
July 06, 2023Compliance Inspection
-
March 19, 2023Date Start of Construction Notice Rec'd
-
March 10, 2023FWW Permit with Variance Issued
-
March 09, 2023Application Review by Supervisor
-
March 08, 2023Application Review by Biologist
-
March 06, 2023Application Review by Engineer
-
February 22, 2023Applicant Response to Tech. Deficiency
-
February 15, 2023Technical Deficiency Letter Sent
-
February 15, 2023Application Review by Biologist
-
February 06, 2023Application Review by Engineer
-
January 23, 2023Applicant Response to Tech. Deficiency
-
January 04, 2023Technical Deficiency Letter Sent
-
January 04, 2023Application Review by Biologist
-
December 13, 2022Application Review by Engineer
-
December 01, 2022Response to Administrative Deficiency
-
November 30, 2022Additional Info Received during Review
-
November 15, 2022Administrative Deficiency Letter Sent
-
November 02, 2022Application Review by Engineer
-
October 31, 2022Supervisor for Assignment
-
October 26, 2022Additional Info Received during Review
-
October 06, 2022FWW Permit with Variance APP Rec'd
-
October 06, 2022Freshwater Wetlands Permit App Rec'd
-
June 23, 2022Pre-Application Meeting Held
Need to Review a File? Email a Request for Records Form to DEM.FileReview@dem.ri.gov.
For wetlands questions, please visit dem.ri.gov/wetlands or email DEM.FWW@dem.ri.gov.Last updated 04-08-2026 05:43 PM