DEM Wetland Application Search

DEM Wetland Application #24-0140

  • Applicant name
  • Organization name Rhode Island Energy
  • Location L14 & M13 Tiverton Tap Tiverton
  • Project information Tiverton Tap Rebuild Project - Utility (Electric)
  • Plan View
  • DEM Letter View

Location description

Within a Rhode Island Energy Right-of-Way, beginning east of Fish Road and extending north to the Rhode Island-Massachusetts State Line, Tiverton, RI

Historical information

  • November 15, 2024
    Date Start of Construction Notice Rec'd
  • November 13, 2024
    Permit Recorded in Land Evidence Record
  • November 12, 2024
    FWW Permit with Variance Issued
  • November 12, 2024
    Application Review by Supervisor
  • November 06, 2024
    Application Review by Biologist
  • October 30, 2024
    Applicant Response to Tech. Deficiency
  • October 18, 2024
    Technical Deficiency Letter Sent
  • October 10, 2024
    Application Review by Biologist
  • October 08, 2024
    Applicant Response to Tech. Deficiency
  • September 20, 2024
    Technical Deficiency Letter Sent
  • September 05, 2024
    Application Review by Biologist
  • June 24, 2024
    Supervisor for Assignment
  • June 10, 2024
    Freshwater Wetlands Permit App Rec'd
  • May 24, 2024
    Pre-Application Meeting Held

Need to Review a File? Email a Request for Records Form to DEM.FileReview@dem.ri.gov.

For wetlands questions, please visit dem.ri.gov/wetlands or email DEM.FWW@dem.ri.gov.
Search criteria
Last updated 04-08-2026 05:43 PM
powered by ri.gov