DEM Wetland Application #24-0250
- Applicant name
- Organization name The Narragansett Electric Company
- Location Central Johnston
- Project information Johnston Tap T172S-1&S171-1 115 kV Rbld - Utility (Electric)
- Plan View
Location description
Along the T172S-1/S-171-1 Johnston Tap Line Right-of-Way (ROW), beginning at the Johnston Substation #18 located at 165 Central Avenue, and continuing west along the ROW and ending approximately 100 feet west of Route 295 and approximately 800 feet northwest of the 295 overpass over Central Avenue, Johnston, RI.
Historical information
-
February 28, 2025FWW Permit with Variance Issued
-
February 28, 2025Application Review by Supervisor
-
February 25, 2025Application Review by Biologist
-
February 18, 2025Applicant Response to Tech. Deficiency
-
February 14, 2025Technical Deficiency Letter Sent
-
February 14, 2025Application Review by Biologist
-
January 03, 2025Applicant Response to Tech. Deficiency
-
December 09, 2024Technical Deficiency Letter Sent
-
December 09, 2024Application Review by Biologist
-
November 13, 2024Supervisor for Assignment
-
November 06, 2024Response to Administrative Deficiency
-
October 24, 2024Administrative Deficiency Letter Sent
-
October 24, 2024Supervisor for Assignment
-
October 16, 2024Freshwater Wetlands Permit App Rec'd
Need to Review a File? Email a Request for Records Form to DEM.FileReview@dem.ri.gov.
For wetlands questions, please visit dem.ri.gov/wetlands or email DEM.FWW@dem.ri.gov.Last updated 04-08-2026 05:43 PM