DEM Wetland Application #94-0272F
- Applicant name
- Organization name RIDOT
- Location Smithfield
- Project information - Road Reconstruction
Location description
along the length of U.S. Route 44 (Putnam Pike) extending from its intersection with Interstate Route 295 to its intersection with West Greenville Road, Smithfield, R.I.
Historical information
-
July 17, 2000Permit Renewal Granted
-
July 17, 2000Application Review by Supervisor
-
June 07, 2000Application Review by Biologist
-
January 26, 2000Application Review by Supervisor
-
January 19, 2000Request to Renew Permit
-
September 07, 1999Modification Approved - Permit Issued
-
September 03, 1999Application Review by Supervisor
-
August 17, 1999Application Review by Biologist
-
August 16, 1999Application Review by Engineer
-
August 10, 1999Application Review by Biologist
-
July 20, 1999Applicant Response to Tech. Deficiency
-
February 19, 1999Technical Deficiency Letter Sent
-
February 19, 1999Permit Renewal Granted
-
February 19, 1999Application Review by Supervisor
-
February 18, 1999Application Review by Biologist
-
January 19, 1999Application Review by Engineer
-
December 16, 1998Nonconformance with Permit
-
December 15, 1998Application Review by Supervisor
-
December 04, 1998Compliance Inspection
-
December 04, 1998Application Review by Biologist
-
November 09, 1998Application Review by Supervisor
-
October 27, 1998Request to Modify Wetland Permit
-
October 27, 1998Request to Renew Permit
-
August 10, 1998Date Start of Construction Notice Rec'd
-
February 26, 1998Permit Renewal Granted
-
February 25, 1998Application Review by Supervisor
-
January 28, 1998Request to Renew Permit
-
March 19, 1997Alteration Permit Issued
-
March 17, 1997Supervisor Review of Alteration Project
-
January 28, 1997Comments Received
-
January 28, 1997Public Notice Comment Review
-
January 10, 1997Biologist Evaluation
-
September 19, 1996Engineering Evaluation
-
August 26, 1996Public Notice End Date
-
July 12, 1996Public Notice Issued
-
July 10, 1996Application Review by Supervisor
-
July 05, 1996Public Notice Plan Review
-
June 28, 1996Plans Received for Public Notice
-
May 23, 1996Adequate for Public Notice
-
May 22, 1996Application Review by Supervisor
-
April 17, 1996Application Review by Biologist
-
April 16, 1996Application Review by Engineer
-
April 12, 1996Application Review by Biologist
-
April 09, 1996Applicant Response to Tech. Deficiency
-
March 27, 1996Technical Deficiency Letter Sent
-
March 26, 1996Application Review by Biologist
-
March 22, 1996Application Review by Engineer
-
March 20, 1996Application Review by Biologist
-
February 23, 1996Applicant Response to Tech. Deficiency
-
January 05, 1996Technical Deficiency Letter Sent
-
January 05, 1996Application Review by Biologist
-
December 27, 1995Application Review by Engineer
-
October 25, 1995Application Review by Biologist
-
August 03, 1995Applicant Response to Tech. Deficiency
-
June 13, 1995Technical Deficiency Letter Sent
-
June 13, 1995Application Review by Biologist
-
May 09, 1995Application Review by Engineer
-
April 24, 1995Application Review by Biologist
-
March 20, 1995Applicant Response to Tech. Deficiency
-
September 08, 1994Technical Deficiency Letter Sent
-
September 06, 1994Application Review by Biologist
-
August 30, 1994Application Review by Engineer
-
August 17, 1994Application Review by Biologist
-
June 28, 1994Response from Applicant
-
June 14, 1994Technical Deficiency Letter Sent
-
June 13, 1994Application Review by Biologist
-
June 06, 1994Request to Alter Wetland Application